Installation


Corridor Swing 600
Self-supporting



Storage & Installation
Storage and installation should not be carried out in rooms with a relative humidity greater than 70%, unless otherwise stated, see section Moisture. It is equally important to take account of other work such as technical installations before installation of the ceiling is carried out. It is important for the end result that the ceiling tiles are installed at right-angles, this makes installation quicker and easier. It will facilitate inspections to installations above the ceiling as removal of the tiles will be easier. It is not recommended that ceilings are installed at a temperature consistantly over 50°C.
Dimensional out-line, wall junction
M indicates the module line. There must be a 12 mm gap on each side of M. The metal clip, 721175 is fixed to the wall at 800 c/c mm and the W-swing 2 profile is fixed to the metal clip with the W34 bolt.
Dimensional out-line, Fixed frieze
M indicates the module line. There must be a 12 mm gap on each side of M. The metal clip, 721175 is fixed to the vertical profiles and horizontal U-profiles are installed so the fixed frieze can be screwed onto them. The W-swing 2 profile is fixed to the metal clip with the W34 bolt.
Dimensional outline, Dismountable frieze
M indicate module line. There must be a 12 mm gap towards the Corridor swing element and a 18 mm gap to the frieze. Horizontal U-profiles and vertical C-profiles are installed in order to create a rigid frame for the swing profiles. W-swing 2 and 4A profiles are fixed at c/c 800 mm in the vertical steel profiles with the W34 bolt. The wall angle is fixed to the wall at c/c 400 mm.

Planning the ceiling surface
The module measurement is 24 mm larger than the actual elements. When installed there will be 24 mm gab around all edges of the element.
Profile distances
The W swing 2 profiles are installed under the metal clips with the W34 clip. Now the distance between the “suspension points” on the W swing 2 profiles must be adjusted, so the distance between them is the length of the element minus 50 mm. The two swing profiles must be installed, so the suspension points are directly opposite each other due to the following installation of the actual elements.

Fixing of the metal clip
The metal clip is fixed to the wall or vertical steel profiles at c/c 800 mm. The lowest edge of the metal clip should be 65 mm higher than the desired ceiling height. It is very important that the frame work is rigid so it cannot deform the elements when installed.
Assembly of the elements
The elements come with depressed fittings. The SW15 profiles are fixed with the supplied screws through the depressed fitting into the element. The distance between the end of the profile to the edge of the element must be 15 mm. Only one SW15 swing profile is fixed at this stage. The base for fixing the load bearing profiles must be plane and solid. There must be no deflection of the profile during the fixing of it.
Installation of swing hanger SW6MB
The swing hanger is fixed to the fastened SW15 profile, the other SW15 swing profile is pushed into its slot, so the hanger is fixed in the hole of the SW15 profile. Now the other SW15 profile can be fixed using previous described method. It is not recommend installing the hanger by tensioning as it will give an inappropriate sideways force on the SW15 profiles.
Installation of Swing cross profile
The cross profile is placed onto the metal clip so that the hole in the cross profile is directly above the centre hole in the metal clip. The foil cover is removed from the adhesive pads and the cross profile is pressed tightly against the element. The screw is fixed through the hole in the profile and the centre hole in the metal clip.
Installation of the elements
The ceiling elements are hung along one of the sides to begin with. The element is kept vertical with the hanger pointing up and the hanger is clasped on the W-swing 2 profile.
Finishing the installation
The element is swung up to horizontal level and the hangers are held in vertical position so it can be slid into the W-swing 2 profile.